VFW Post needs legal advice

Status
Not open for further replies.

abono

New Member
Hi,

I'm the Senior Vice Commander of a VFW Post on Long Island, and recently we re-furbished our bathrooms. We hired a contractor to do the job, and he intern sub contracted a company to install individualized stalls in the bathrooms. The renovations were finished, and we paid our contractor in full. After we paid our bill the contractor we hired went out of business and never paid the sub contractor for the partitions he installed in our bathrooms. The partition installer has already put a lien on our property, and is now threatening to come into our post and remove the bathroom partitions. Is there some way we can protect our selves from the partition installer? We were thinking of a Restraining Order. Does Restraining Orders cover things like this, and how do we go about getting a Restraining Order?

Thanks,
Anthony Bono
 
Did y'all sign an agreement BEFORE the work was started, allowing mechanic's liens to be filed against you?

Did y'all get LIEN WAIVERS whenever you paid the contractor?

How do y'all know that a lien has been filed?

Have y'all seen it?

What does it say?
 
1. Before the work started we did not sign any agreement allowing mechanic's liens.

2. We did not get lien waivers after we paid our contractor.

3. We received a form (certified mail) called "Notice Under Mechanic's Law". In that form our VFW Post is the subject of the lien. The notice goes on to say that the company that installed the partions was hired by our contractor, and not by the VFW.

4. The amount of the lien is $800.00
 
For those who work on construction jobs, getting paid is certainly far better than the alternative. Creditors with a lien are in a much better position to be paid, particularly if a bankruptcy filing enters the equation. It is critical, therefore, for creditors to understand their rights under New Jersey law.

The New Jersey Construction Lien Law (the "Lien Law") replaced the old Mechanic's Lien Law in 1994. Neither of these laws is applicable to public projects. The new Lien Law (N.J.S.A. 2A:44A-1 et seq.) eliminated the filing of a Mechanic's Notice of Intent. Instead, it is necessary to file certain information within 90 days following the date of the last work, services, materials or equipment provided with the Clerk of the county in which the property is located.

A lien claim may only be filed if there is a written contract between the lien claimant and its customer (whether it be the owner, contractor or subcontractor). A lien claimant will lose any rights that it may have to enforce the lien, and the lien itself, if legal action is not instituted within one year of the date of the last work under the contract. The one-year time period starts from the time of last work or services provided, not from the date of the filing of the lien.

If the project is "commercial", as opposed to "residential", a lien claimant is entitled to, but is not required to, file a "Notice of Unpaid Balance and Right to File Lien" (NUB). A NUB is also filed with the Clerk of the county in which the property is located.

A lien claimant must take additional steps on a residential project. The Lien Law includes the following under the definition of residential: a one- or two-family dwelling; a condominium; a housing cooperative; and a townhouse development. However, the distinction between residential and commercial is not clear under the law, particularly with respect to work performed on common elements such as drainage and streets.

If work is done under a residential construction contract, the lien claimant must do more to insure that the lien is properly filed and perfected. These steps include: filing a NUB; serving a Demand for Arbitration under the American Arbitration Association program created for residential construction lien claims, and then, if successful in the Arbitration, filing the lien claim with the Clerk in the county in which the property is located. All of these steps must be completed within 90 days from the date of the last work, services, material or equipment provided.
A Bankruptcy Judge in New Jersey recently ruled that lien claimants on what arguably was a commercial project had to follow the residential lien requirements, which included a NUB filing. It was also ruled that if the lien filing process was not completed before the bankruptcy petition was filed, the creditor did not have a valid lien. It is therefore very important to address payment and lien issues promptly and aggressively or your lien rights may be lost.



This is info from a law firm that I know nothing about so I am not giving you the cite.

In any event, surely one of your members is a lawyer or there is a lawyer in another post who would help you.

You have a problem....
 
Thanks for the info. Hopefully, my state, New York, has the same laws concerning liens as New Jersey. Your third paragraph may prove especially useful.

We are not too concerned with the lien because the VFW will never sell the property, and as a result we could fight the lien when we get our ducks in a row - so to speak. Our primary concern is how do we protect ourselves from the contractors threats to forcibly uninstall the bathroom partitions.
 
Sorry...I thought you were in New Jersey....

But the answer is the same.

Get a lawyer.

You don't want this guy selling your clubhouse on the courthouse steps!
 
Status
Not open for further replies.
Back
Top